Mumbai: The prestigious Mumbai Trans Harbour Link (MTHL) is racing towards completion with 96.60% progress achieved, four months after the bridge superstructure was completed in end-May, officials said here on Friday.
Mumbai Metropolitan Region Development Authority (MMRDA) Commissioner Sanjay Mukherjee carried out a comprehensive inspection of the current status of the mega-project along with other senior officials as the MTHL rushed to meet the tentative November opening deadline announced earlier.
The 22-km, India’s longest sea bridge will connect Mumbai Navi Mumbai on the mainland and drastically travel time to various points in the state.
The project includes a total of 1,212 lighting poles of which 20 percent are already in place, said Dr. Mukherjee.
These lighting poles are equipped with a Central Control & Monitoring System and are specifically designed to withstand the challenges of being situated in the deep sea.
The poles are suitable for a saline environment, with a corrosion-free polyurethane coat, galvanization to prevent rush and prolong lifespan, structural design to withstand high winds, uniform illumination all across the sea link and shall come with a Lightning Protection System to safeguard against possible lightning strikes.
The MTHL was executed in three packages for civil works and a fourth package focussing on the Intelligent Transport System, an Automated Toll Collection System and electrical works.
In a pioneering application in India, the bridge itself utilizes Orthotropic Steel Deck (OSD) spans, ranging from 65m to 180m in length, and serves as a testament to the use of unique products and state-of-the-art construction methods, said Dr. Mukherjee.
Once operational, the MTHL will provide faster connectivity to the upcoming Navi Mumbai International Airport, the JNPA Port, Mumbai-Pune Expressway, Mumbai-Goa Highway and other locations, contributing to the growth and development of the region.
–IANS
Comments are closed.