Shree Mandira Parikrama Project: 5T Chairman Directs to Complete Buffer Zones, Landscaping Zones Early by Next Week
Bhubaneswar: 5T & Nabin Odisha Chairman VK Pandian today inspected Shree Mandira Parikrama Project and reviewed queue management and traffic control around the temple for smooth and safe entry of pilgrims into the temple.
He reviewed various segments of the project on early morning from 7 AM to 9 AM.
He conducted a thorough review of the project’s progress, landscaping works, matha restoration, Queue management system from Shree Parking(JBPC) & Marichikote to Dolabedi.
Some key decisions were taken and directives were given accordingly.
He emphasized on substantial progress on Dolabedi restoration, Emar matha, Panjabi Matha, Uttarparswa matha and façade painting around the Parikrama.
He also inspected and reviewed the landscaping done in different patches of South, West and North and directed to complete substantially the buffer zones and other landscaping zones on all sides by next week.
He also stressed completion of Effluent Treatment Plant (ETP), garbage chutes, shifting of sub-station on decided time.
The 5T Chairman urged timely completion of the electrical works & shifting of utilities near Meghanad Pachiri.
He visited Jagannath Ballav area, Shree Marga and development of Pramod Udyan and instructed to expedite all works.
Among others, Collector of Puri; SP, Puri, Managing Director, OBCC; and other officials were present.